A factory lighting installation example is most useful when it shows the decisions behind the result, not just the fittings installed. In a working facility, lighting affects picking accuracy, machine safety, quality checks, forklift movements, maintenance access and energy expenditure. The right outcome is a measured upgrade that delivers suitable illumination where people work, with less power and fewer maintenance interruptions.

Consider a representative 6,000 m² manufacturing and warehousing facility in NSW. The site has 9 metre mounting heights, four loading bays, racking through part of the warehouse, assembly benches, a dispatch zone and a small plant room. Its existing metal halide high bays are nearing end of life. Light levels are inconsistent, lamps require frequent replacement and the lighting load operates for two shifts, six days a week.

The project objective is not simply to replace every existing fitting with an LED equivalent. It is to establish the required light levels by task, reduce connected load, maintain safe access and deliver a system that can be serviced over its operational life.

Factory lighting installation example: project scope

The first stage is a site audit. This records the existing fitting types, wattages, mounting heights, circuit arrangements, operating hours and condition of switchboards and cabling. It also identifies areas where lighting performance has a direct operational effect, such as receiving, production lines, inspection stations and pedestrian routes.

For this example, the audit finds 120 metal halide high bays rated at 400 W, plus ageing fluorescent fittings in the office-adjacent packing area and exterior floodlights at the loading docks. Allowing for control gear, the high-bay system draws materially more power than the lamp rating alone suggests. Several fittings are also obscured by racking or poorly positioned over aisles, leaving shadowed work areas despite high energy use.

A lighting design then divides the building into functional zones rather than treating the factory floor as one open space. The warehouse aisles require uniform vertical and horizontal light for labels and stock handling. Assembly and quality-control benches need higher, more controlled illumination. Loading bays require clear visibility around dock edges, trailer doors and pedestrian crossings. Plant rooms demand durable fittings suitable for their environment.

The design should be assessed against the relevant requirements of AS/NZS 1680, with the final specification reflecting the site activity, room geometry and risk profile. Electrical installation work must also be planned and completed in accordance with applicable requirements, including AS/NZS 3000. Where emergency lighting is part of the scope, it needs its own assessment, testing and compliance pathway rather than being treated as an add-on to general lighting.

The proposed LED solution

In this scenario, the lighting plan replaces the 120 metal halide fittings with 96 LED high bays. The lower fitting quantity is possible because the proposed optics, mounting locations and light distribution have been designed for the layout rather than copied from the old grid. A photometric calculation verifies average illuminance, uniformity and glare considerations before products are ordered.

The main warehouse receives 150 W LED high bays with a distribution suited to the racking layout and 9 metre mounting height. The assembly zone uses higher-output high bays with improved colour rendering, allowing operators to distinguish components, markings and surface conditions more reliably. The packing area receives linear LED battens or low-bay fittings selected for lower mounting heights and close visual tasks.

At the loading docks, weatherproof LED floodlights are positioned to illuminate the working plane without creating excessive glare for truck drivers or staff moving between indoor and outdoor areas. The plant room receives IP-rated LED fittings matched to dust, moisture and ambient temperature conditions.

Controls are included where they serve the operation. Occupancy sensors are appropriate in intermittently used stores, amenities and plant rooms. Daylight harvesting can work well near skylights or translucent roof panels, provided the sensors are commissioned carefully and do not cause distracting changes in output. Main production areas operating continuously may gain more value from zoning and scheduling than from occupancy sensing.

This distinction matters. Controls can produce worthwhile savings, but only when they match how the area is used. An over-complicated control system can create staff frustration, call-outs and bypassed settings. A dependable, clearly labelled arrangement is usually the better commercial choice.

Installation planning around production

A factory cannot always shut down for lighting works. Installation planning therefore starts with access, isolation and production constraints. For the example facility, works are staged by warehouse zone during scheduled maintenance windows and lower-activity periods. This keeps forklifts, production equipment and dispatch operations operating where safe to do so.

Before installation, the contractor confirms ceiling structure, lifting access, cable routes, circuit capacity and isolation points. Existing mounting points are inspected rather than assumed to be suitable for the new fittings. Where elevated work platforms are required, exclusion zones are marked below, and the work sequence is coordinated with site supervisors.

The installation team removes redundant fittings progressively, installs the new high bays, completes wiring and labels circuits for ongoing maintenance. In some projects, retained circuits can be used to maintain temporary lighting while adjacent areas are upgraded. This depends on the existing electrical configuration and must not compromise safety or testing requirements.

A practical installation programme also accounts for disposal. Legacy lamps, control gear and damaged fittings should be handled through appropriate waste streams. This is particularly relevant where older lamps or fittings contain materials that should not enter general rubbish.

Measuring the operational result

The proposed high-bay upgrade reduces the nominal high-bay connected load from approximately 48 kW to 14.4 kW. Actual savings depend on driver losses, operating hours, control settings and the condition of the existing system, but the reduction in lighting energy use can be substantial for a two-shift factory.

The more meaningful measure is the whole operating outcome. After commissioning, light levels should be checked at representative work areas, including aisles, benches, dock faces and circulation paths. Facilities teams should confirm that switches, sensors and emergency lighting indicators are understood, accessible and recorded in site maintenance procedures.

Maintenance requirements also change. LED high bays generally offer longer service life than metal halide systems, reducing the frequency of elevated access work and lamp replacement. However, long life does not eliminate maintenance planning. Drivers, sensors, emergency components and external fittings still require inspection, while dust accumulation can reduce delivered light in dirty environments.

Energy savings may also be eligible for support through applicable state energy-efficiency schemes, subject to the project, equipment and current scheme rules. Early assessment is preferable because eligibility, documentation and installation requirements can influence product selection and programme timing. An accredited provider can help determine whether a proposed project is suitable before the work is committed.

Design choices that change the outcome

There is no single high-bay wattage that suits every factory. A facility with 12 metre ceilings, narrow racking aisles and continuous forklift traffic needs a different optical approach from a food-processing site with washable surfaces or a fabrication workshop with high visual-detail tasks.

Colour temperature is another example. A neutral to cool white light is commonly selected for industrial work areas because it supports clarity and alertness, but the final choice should consider the task, finishes and employee comfort. Higher colour rendering is valuable for inspection, paint matching and product assessment, though it may involve a cost or efficiency trade-off depending on the product range.

The cheapest fitting on the schedule can be the most expensive decision over the life of the installation if it delivers poor uniformity, inadequate ingress protection or unreliable drivers. Product selection should consider photometric data, warranty terms, thermal performance, surge protection, mounting options and the availability of replacement components. For projects with multiple work zones, a mixed fitting schedule is often more effective than forcing one product across the entire site.

Handover that supports long-term performance

A factory lighting project should finish with more than a new, bright floor. The handover should include fitting schedules, circuit information, control settings, test results, warranty details and maintenance recommendations. This gives facilities managers a clear record for future servicing, tenancy changes and compliance activities.

EO Lighting can support this process from site audit and lighting design through to supply, installation and ongoing service, providing a single point of accountability across the project.

The strongest factory lighting upgrades are built around the work being done beneath them. When the design follows the layout, task requirements and operating hours of the facility, lower energy use becomes a practical result of better lighting rather than the only measure of success.